Integration Projects, civil construction and electromechanical erection with the supply of equipment and materials, of transmission lines of high and extra voltage, 4.725 Km4.725 Km of totting up lines built.

Major works:

Furnas Centrais Elétricas S/A
  • Civil construction and electromechanical erection with partial supply of materials of LT 500kV
  • Cachoeira Paulista - Areias - São Paulo
  • 120 Km

Eletronorte – Centrais Elétricas do Norte do Brasil S/A

  • Civil construction and electromechanical erection with partial supply of materials 500kV
  • Stretch III of Integration North South I (indicate the status)
  • 84 Km

Sistema de Transmissão Nordeste S/A

  • Executive design, civil works, electromechanical erection and total supply of materials in turn-key contract LT 500 kV
  • Teresina (PI) - Sobral (EC) - Fortaleza (CE)
  • 545 km

Empresa Norte de Transmissão de Energia S/A

  • Executive design, civil works, electromechanical erection and total supply of materials in turn-key LT 500
  • Tucurui (PA) – Açailândia (MA)
  • 468 Km